NAME OF PROJECT
|
TYPE OF INDUSTRY
|
LOCATION
|
CUSTOMER
|
YEAR
|
TYPE OF WORK
|
CONTRACT VALUE
RM
|
MG3 Lube Base Oil Plant, Melaka |
Petroleum Refinery |
Melaka |
PT Technic |
Apr-07 (on-going) |
Supply & installation of Hot Insulation for Storage Tanks |
|
PDOC Petrodar Pumping Facilities |
Gas Plant |
Sudan |
Betini-NF Energy JV |
May 05 (8 months) |
Supply & installation of insulation work. |
|
Ammonia & Urea Plant Revamp Project |
Ammonia, Urea & Fretilizer |
Bintulu |
Asean bintulu Fertilizer |
Jan 04 |
Supply & installation of hot and cold insulation work. |
|
|
LNG Plant |
LNG Plant |
LNG Plant |
|
|
Malaysia LNG Sdn Bhd & KBR(consultant) |
Malaysia LNG Sdn Bhd & KBR(consultant) |
Malaysia LNG Sdn Bhd & KBR(consultant) |
|
Sep 02 - Oct 03 |
Sep 02 - Oct 03 |
Nov 02 - Dec 03 |
|
Rejuvenation & revamp of existing plant - "LIVE PLANT".
Supply & installation of hot and cold insulation work.
RM12,000,000 |
Supply & installation of hot and cold insulation work, red lead
removal, painting, structural steel rejuvenation, fire-proofing
and scaffolding.
RM35,000,000 |
Supply & installation of hot and cold insulation work including
removal of existing insulation,, red lead removal, painting and
scaffolding
RM28,000,000 |
|
|
Malaysian Olefin Project |
Ethane/Propane Cracker Plant |
Kerteh |
Samsung Engineering (M) Sdn Bhd |
Jul 00 - Apr 02 |
Supply & installation of hot and cold thermal insulation works for
piping & equipment at Heater/Quench area |
|
Butanol/Derivatives Facilities Project |
Ethylene Oxide Glycol & Butanol Plant |
Kerteh |
Bechtel Bina (M) Sdn Bhd |
Jul 00 - Jun 02 |
Supply & installation of hot and cold thermal insulation works for
piping & equipment including fireproofing for equipment |
|
BASF Petronas Chemical Acrylics Complex
|
Acrylics Plant
|
Gebeng Kuantan
|
Bechtel-Shapadu Consortium
|
May 99 - Apr 00
|
Supply & installation of hot and cold thermal insulation
works for piping & equipment
|
|
Malaysian Polyplastic Project MP-1
|
Polyplastic Plant
|
Gebeng Kuantan
|
Equator Engineering Sdn Bhd
|
May 99 - Dec 99
|
Supply & installation of hot and cold thermal insulation
works for piping & equipment
|
|
Kerteh Aromatics KR 2
|
Aromatic Plant
|
Kerteh
|
Toyo Engineering Corporation
|
Nov 98 - Mar 00
|
Supply & installation of thermal insulation for piping & equipment
including fireproofing and painting of equipment
|
|
Kerteh Vinyl Chloride KVCM |
Vinyl Chloride Monomer Plant |
Kerteh |
Toyo Engineering Corp |
Jan 99 - Mar 00 |
Supply & installation of thermal insulation for piping & equipment
including fireproofing for equipment |
|
Petronas Fertilizer PFK Project
|
Fertilizer Plant
|
Gurun Kedah
|
Mitsubishi Heavy Industries Ltd
|
Feb 98 - Oct 98
|
Supply & installation of hot and cold thermal insulation
works for piping & equipment
Supply & installation of cryogenic insulation works for
2 units Ammonia Tanks
Supply of labour & equipment for Reformer refractory works
|
|
PGU II - Stage 2 System 2(GPP 5 & 6)
|
Gas Plant
|
Kerteh
|
Daelim Engineering / Meisei Industrial
|
Mar 97 - Nov 99
|
Supply & installation of hot and cold thermal insulation
works for piping & equipment
|
|
Kaneka Malaysia Project
|
Polymer Plant
|
Gebeng Kuantan
|
Equator Engineering Sdn Bhd
|
Jul 97 - Dec 97
|
Supply & installation of hot and cold thermal insulation
works for piping & equipment
|
|
Ethylene(Malaysia) Sdn Bhd
|
Ethylene Plant
|
Kerteh
|
Nichias Corporation
|
Oct 94 - Jun 95
|
Supply package for prefabricated foamglas for process area
piping and equipment
|
|
Ethylene(Malaysia) Sdn Bhd
|
Ethylene Plant
|
Kerteh
|
Meisei Industrial Co Ltd
|
Oct 94 - Apr 95
|
Supply package for prefabricated foamglas for UT/OS area piping
and equipment
|
|
Dew Point Control Unit 2 - PGU II Stage 2, System 2
|
Gas Plant
|
Kerteh
|
Equator Engineering Sdn Bhd
|
Mar 94 - Aug 95
|
Supply & installation of hot and cold thermal insulation
works for piping & equipment
|
|
PGU II - Stage 2 System 2 (GPP 4)
|
Gas Plant
|
Kerteh
|
Hyundai Engineering & Construction Co Ltd
|
Sep 93 - Jun 94
|
Supply & installation of hot and cold thermal insulation
works for piping &am; equipment
|
|
PGU II - Stage 2 System 2 (GPP 2 & 3 )
|
Gas Plant
|
Kerteh
|
Hyundai Engineering & Construction Co Ltd
|
Apr 91 - Aug 92
|
Supply & installation of hot and cold thermal insulation
works for piping & equipment
Supply & installation of passive fire proofing for equipment,structural
steel and spherical tanks
|
|
Tank 10 Insulation |
Petroleum Refinery |
Port Dickson |
Esso Malaysia Berhad |
Sep-89 |
Supply & installation of thermal insulation works for storage tank. |
|
Petronas Kerteh Reformer
|
Petroleum Refinery
|
Kerteh
|
Chiyoda Corporation
|
Jul 89
|
Supply & installation of thermal insulation works for
hot piping & equipment
Refractory lining of reformer / fire heaters, hot air ducts
and chimney
|
|